Ravenswood School
Chicago Public Schools
- Removed old, leaking boiler bottom from 1935 vintage Kewanee boiler.
- Fit up and fabricated new boiler bottom into the existing pressure vessel.
- The new work was pressure tested and inspected by a licensed City of Chicago boiler inspector.
- This project allowed the school to use the existing boiler another 20 plus years without having to spend hundreds of thousands of dollars on a new boiler system.